A client of our bureau recently requested a change of legal address, submitting an application to the Unified State Register of Legal Entities on 7 February 2024. The tax authority implemented the changes on 14 February 2024 at 07:43. The registration was completed successfully, and the company commenced operations at the new address. However, at…

A network organization and a gardening non-profit partnership (GNP) concluded several contracts under which the GNP undertook to build a power transmission line (PTL). In fact, these contracts had the same subject and duplicated each other (the obligation to build the same PTL), but due to the oversight of the parties when concluding duplicate contracts,…

The developer of the cottage village founded a non-profit gardening partnership (NGP) in the built-up village and leased public land to it for a nominal fee. Then, on these lands, a highway was built, reflected in the land planning documents and the urban development plan. After a while, the developer went bankrupt. As a result…

On December 5, 2024, the annual award ceremony for the winners of the “Pravo-300” rating took place, which for 15 years has served as a benchmark of quality for the Russian legal services market. Recognition within the rating confirms the high level of qualification of experts, their professionalism, and competence in solving the most complex…

The client of our bureau – a company registered under the laws of Kazakhstan, applied to a Kazakh carrier with a request for the carriage of goods from the territory of Kazakhstan to a warehouse located in the territory of Russia. The carrier received an advance payment from our client, accepted the cargo and transported…

A consumer ordered the construction of a country house from our client, the contractor’s materials. During the work, the consumer expressed dissatisfaction with the quality of the material and the fact that the work was taking too long, after which the consumer decided to abandon the construction and demanded the return of the advance payment,…

Even after the deadline for construction work under the state contract, the customer and the contractor concluded an additional agreement to increase the scope of work without extending the deadline for their completion. This amount of work could not objectively be completed on time, since at the time the contractor assumed these obligations, the deadline…

In 2022, in a large food company, corporate control passed from foreign owners to Russian management. To optimize costs, the company decided to restructure its operations, including the transfer of all administrative and managerial functions to the head office in St. Petersburg. In this regard, the position of legal counsel at a production enterprise in…

Our client ordered equipment from a supplier to support his production activities. The terms of the order were agreed upon by the parties through an exchange of letters and e-mail messages without drawing up a contract in the form of a single written document. The goods did not arrive within the agreed time frame, so…

One of our clients has done work for a large industrial enterprise on the software configuration of production equipment. After receiving the final service report, the customer stopped contacting, without paying the contractor the remaining part of the cost of the main volume of work accepted by the act, and without confirming the additionally performed…

Page 2 of 14 1 2 3 4 14
logo-footer
Мы используем cookie-файлы для лучшего представления нашего сайта.
Принять