The client of our bureau, that specialises in providing warehousing services, for a long time provided such services to a car manufacturing company in St. Petersburg. When the contract was about to expire, the company decided not to prolong it and to move its goods to another warehouse. However, the removal of the goods was…

Even after the deadline for construction work under the state contract, the customer and the contractor concluded an additional agreement to increase the scope of work without extending the deadline for their completion. This amount of work could not objectively be completed on time, since at the time the contractor assumed these obligations, the deadline…

On April 18-19, 2024, the International Scientific Conference “Religion, Worldview and Pure Doctrine of Law” was held at the Faculty of Law of the Higher School of Economics – St. Petersburg, the sponsor of which was our bureau. The conference was devoted to the discussion of the development of fundamental jurisprudence in the context of…

A company engaged in the construction of seagoing vessels ordered equipment from a subcontractor to equip a seagoing vessel supplied under a state defense order contract to a state customer. Since the equipment was not delivered on time, the company demanded the return of the unspent advance. The subcontractor, without disputing the violation of the…

The client of our bureau has assumed obligations under a state contract with an educational institution, but was unable to fulfill these obligations on time. In this regard, the educational institution terminated the contract and applied to the Administration of the Federal Antimonopoly Service of St. Petersburg with a demand to include the contractor in…

The company under several contracts performed a set of works for the customer to prepare for drilling water wells and develop relevant projects. For all contracts, except one, the work was accepted and paid for. The customer refused to accept the work only for the site for which they could not obtain drilling permits in…

One of our company’s clients is engaged in the manufacture of expensive gift watches. As part of one of the orders, a batch of watches was manufactured and transferred to a legal entity-customer on the terms of a 50% prepayment. The customer accepted the watches they ordered, but was in no hurry with the payment,…

Under the contract for the performance of survey and design work, the customer did not pay our client the cost of this work, although the work itself was accepted without comments. The customer referred to difficulties with funding from the budget and asked to wait. For a long time, our client waited, but in the…

As a result of the audit of the documentation in our client’s company, serious financial irregularities were revealed on the part of former employees who previously held senior positions. In one of the cases of violations, it was established that the former deputy general director of the company, while working in the company, created a…

Our client has completed a set of works for the customer to prepare and approve a technological project. After completing the set of works, the client sent the customer acts and certificates in the forms KS-2 and KS-3 for signing. The customer did not sign these documents, did not make objections to the quality of…